Frame Complete
The project has moved forward slowly on two fronts: Bruce’s work on a robust steel frame which defines much of the shape of the forward cabin and Stan and Graham

The project has moved forward slowly on two fronts: Bruce’s work on a robust steel frame which defines much of the shape of the forward cabin and Stan and Graham

5 May, 2006. Efforts to accelerate the construction process have been made during March. Our strategy involves separating the construction work into several independent work packages, and have them carried

Much of the last two months has been spent on the task of obtaining competitive quotes for outsourcing some of the work remaining on the engine, bodywork and steel framing.

A new home for the Starchaser rover has been built by Trinity College in East Perth. The new housing is a colourbond garage with large doors, designed especially for the

The floor frame and two of the vertical bulkhead frames are now complete, but the floor sandwich and radiator frame has yet to be completed.

Further construction work is continuing, slowly. The engine mounting and steel framework is basically complete and work is now proceeding to propeller shafts, steering link and frame for the radiator.